Polyaspartic Polyurea Technical ArticlesHow Should Completed Polyaspartic Polyurea Work Be Accepted? Checking Thickness, Adhesion and Details beyond Ponding Tests
Roof acceptance after a flood test includes membrane thickness, joints and penetrations, terminations and drainage. This guide explains how to check observations, measurements and installation records against the approved details.
Article contents (10 sections)
1. Polyaspartic polyurea acceptance inspection, why can’t we just look at “whether it is leaking now”?
"No water leakage now" is an important result, but acceptance inspection also needs to confirm what materials and construction this result is based on.
If no leak is observed during a roof flood test, record the area tested, duration and observation points. For acceptance, check dry film thickness and continuity, joints and penetrations, terminations and drains against the approved details and installation records. A single flood test cannot establish service life.
For polyaspartic polyurea, Gaodun advocates checking three aspects at the same time: whether the purchased materials are correct, whether the on-site construction is in accordance with compatible system requirements, and whether the completed waterproof layer meets the project acceptance criteria.
This means that acceptance inspection should start from the site entry and construction process, rather than waiting for the last coating to dry before viewing the project for the first time.
2. If the water is closed and the water does not leak, what can it prove?
The ponding test checks for observable leakage under defined areas, water levels, durations and observation conditions.
However, it mainly provides water tightness information under this condition and cannot replace different evaluations such as UV aging, repeated deformation, wear resistance and long-term water immersion.
The disclosure scope of ASTM D5957 includes horizontal waterproofing structures such as designated parking garages or plaza decks with a slope of not more than 2%, and excludes building roofing systems and long-term water storage or continuous submersion conditions. Whether the roof uses water storage, water spraying or other acceptance inspection methods should be determined according to the applicable project specifications and approved plans. Before impounding water, the curing conditions of the structural load-bearing, drainage and waterproof layers should be checked.
Specific projects should determine whether water can be stored, when to start, how to control the water level and duration, and how to observe and drain water based on applicable requirements and product documentation. Roof bearing, temporary water retaining and drainage arrangements should be confirmed by personnel with appropriate capabilities.
The water will not leak once when it is closed, which cannot be directly converted into a service life of ten or twenty years. Long-term reliability also requires evidence of material durability, proper design and construction quality.
3. The coating looks very thick, why do you still need to measure it?
Color, gloss and surface texture can affect visual judgment. The apparent thickness of light-colored, dark-colored and particle-containing coatings may not necessarily correspond to the actual thickness.
"Brushed three times" is not a unit of thickness either. The same three passes of construction, different rollers, operating speeds, substrate roughness and material dilution conditions may result in different final thicknesses.
ASTM D6132-13(2022) introduces the method of measuring organic coating dry film thickness using an ultrasonic thickness gauge. The applicable substrate and coating conditions for the instrument should be confirmed on-site, and then qualified based on the project documents.ASTM D6132-13(2022) Official Summary (store.astm.org)。
For consumers, it is more important to ask the plan to clarify the thickness object: whether it is the main waterproof layer, the total thickness of the entire coating, or the surface height including decorative particles.
Gaodun believes that thickness acceptance inspection should focus on both average conditions and local weak points. Measuring only a few thicker locations does not represent the quality of the film formation on the entire roof.
4. How to check the dosage, wet film and dry film with each other?
The three can supplement each other, but cannot replace each other.
| Check information | What basis can be provided? | Main limitations |
|---|---|---|
| Arrival and remaining material quantities | Estimate on-site material consumption | Including barrel wall residue, loss and different processes |
| Amount per unit area | Determine whether construction significantly deviates from plan | It cannot be proven that the thickness is consistent at every location |
| Wet film thickness | Help control coating during construction | Affected by roughness, test method and cure |
| Dry film thickness after curing | Check the thickness of the finished coating | Applicable instruments, methods and point-taking plans are required |
| Simultaneously produced testimonial site trial | Assists in observing curing and film formation | It cannot directly represent every state of the real roof. |
Under applicable ideal calculation conditions, the theoretical unit area dosage is related to dry film thickness, mixed material density and volume solids content. Actual roofing also has roughness, penetration and loss to consider.
Therefore, you cannot divide the total weight of the purchase by the roof area to directly declare that the thickness is all qualified; nor can you directly use the mass solid content percentage to directly replace the volume solid content to participate in the film thickness conversion.
For concrete substrate, ordinary magnetic instruments for measuring metal paint films cannot be directly copied and used. Methods such as ultrasonic or local sampling also need to be confirmed to be suitable for the specific coating and substrate; when destructive inspection is involved, the repair method should be agreed in advance.
5. Is the higher the adhesion, the better? Does the venue have to hit the advertised numbers?
The evaluation of adhesion needs to look at the value, method and damage location at the same time.
The same coating may get different results when tested on high-strength test panels and old concrete. If the substrate is damaged first when pulling out, the result reflects the load-bearing condition of the test combination at this position. It cannot simply be said that the coating interface has reached a higher value.
ASTM D7234 takes the pull-off strength and failure mode of coating on concrete as evaluation content, and reminds that differences in instruments, substrates and pull-off dollies may affect the results.
Therefore, the adhesion in the laboratory report cannot be turned into a unified acceptance inspection value for all sites without conditions. Site requirements should be determined in advance based on substrate, usage and applicable methods.
For small-area home projects, there is no need to buy your own equipment or cut the coating at will. The project plan can specify whether field pull-off adhesion testing is needed, where to test, how to evaluate the results and how to repair the test areas.
6. Why do drainage outlets, wall roots and ends need to be inspected separately?
The main surface is continuous, which does not mean that all details are continuous.
Wall corners, pipe roots, drainage outlets, thresholds and waterproof ends involve connections in different directions and between different materials. The details processing may also be covered by the subsequent main surface coating, and it is difficult to restore the internal process with the completed photos alone.
Consumers should ask the construction party to keep detailed photos of the processing process and record the laying of reinforcement materials, coating soaking, overlapping and closing. For processes where one fabric layer with three coating applications is applicable, you should also check for dry cloth, wrinkles, hollow-sounding areas or uncoated edges.
The acceptance inspection also confirms the connection between the waterproof layer and the drainage structure: whether the drainage outlet is unobstructed, whether the closing head is firm, and whether there are new obstacles or obvious drainage defects.
The original deformation joints should be inspected according to the special details plan, not just to see whether the surface has been continuously painted.
7. How should we look at pinholes, bubbles and electronic leak detection?
Pinholes, bubbling, abnormal stickiness, cracks and delamination are visible and the causes should be recorded and identified. Whether surface texture or local color difference affects function needs to be judged based on the specific system and cannot be determined solely based on appearance.
For some applicable systems, electronic leak detection can assist in finding discontinuities. ASTM D4787 involves the verification of continuity of liquid or sheet linings on concrete substrates and states that concrete conductivity and its changes can affect detection reliability.
Therefore, electronic leak detection does not mean that one instrument can be used for all roofs. Substrate conductive conditions, coating characteristics, equipment and test parameters all need to match.
After defects are discovered, they should be repaired, cured and reviewed according to the compatible system process. Finding a leak and repairing it does not mean that other areas will automatically pass the acceptance inspection.
8. Consumers can check the acceptance inspection list
| acceptance inspection link | Evidence recommended to be retained |
|---|---|
| Material entry | Model, components, batch, packaging and corresponding technical documents |
| substrate check | Recording of old layer treatment, repair, cleaning and drying conditions |
| Ingredients construction | Proportion size, mixing records, construction date and environmental conditions |
| details processing | Process photos of reinforcement, seams, drains and closing |
| film formation quality | Thickness record, point location and curing status |
| Function check | Applicable water inspection or other testing records |
| Defect handling | Defect locations, repair methods and review results |
| Completed delivery | Conditions of use, maintenance instructions and confirmation records from both parties |
The acceptance inspection document does not have to be complicated, but it should be able to answer: who is inspecting at what location, using what method, what is the result, and whether the problem has been solved.
If you need to lay decorative layers, install equipment or place heavy objects after construction, relevant inspections should be completed first and follow-up construction protection should be agreed upon. After being covered or damaged by other processes, it will be more difficult to trace the responsibility and locate the problem.
9. Why does Gaodun advocate writing the acceptance criteria before purchasing?
For R&D and production companies, delivering a barrel of materials is only part of product application. Clear technical documents and enforceable acceptance criteria help implement material performance into projects and make it easier to identify the true source of quality problems.
Gaodun believes that the direction worthy of continued advancement is to form corresponding records of product batches, construction environments, film thickness distribution, detailed photos and inspection results. Such engineering data can also provide a basis for compatible system optimization and subsequent research and development.
For consumers, before purchasing, they should first confirm the model and applicable substrate, and then agree on the thickness, details, inspection methods and repair review requirements with the supplier or construction party. Long-term performance that cannot be inspected on-site should be evaluated through the testing and application evidence of the corresponding product to avoid being mixed into a completion acceptance inspection.
Reliable polyaspartic polyurea waterproofing delivery should have clear material basis, checkable construction results, and traceable acceptance inspection records.
Note: Specific acceptance criteria are based on applicable project regulations, product documents and engineering plans.
Further reading and technical information
The links below provide background on the topic. When it comes to specific performance, product selection or engineering parameters, please check the applicable objects and test conditions of each data.
- ASTM D7234-22: Pull-off strength of coatings on concrete and failure modes (store.astm.org)
- ASTM D5957: Applicable scope and limitations of horizontal waterproof water storage test (store.astm.org)
- ASTM D4787: Concrete Lining Continuity Test (store.astm.org)
The above original data is used to verify the corresponding technical principles, research formulas or construction examples, and is not the testing or certification of Gaodun products. Research conclusions should be understood together with formulas, specimens and test conditions; construction parameters of products from different manufacturers cannot be directly interchanged.